Skip to content
Fox Glen Association
Fox Glen Association
Online home for Fox Glen Association, Ann Arbor, MI
Skip to content
  • Public info
    • About
    • Management
    • Condo Documents
    • Images
  • For Co-Owners
    • Important correspondence mailed USPS or emailed to co-owners
    • Modification Requests
    • Parking Rules
    • Political signs (free speech)
    • Report a Problem or Create a Work Order
      • View Closed Problems Report
      • View Open Work Requests
    • Leasing
    • Limited Common Elements
    • News items (Posts)
    • Calendar
  • Resources
    • Fox Glen Board
    • Strategic Plan
    • Overall Tree & Landscape Design (OTLD)
    • Aerial view
    • Board Meetings
    • Annual Meetings
    • Proxy Form for Annual Meeting
    • Budgets and Audits
    • Reserve Studies
    • Other Reports
    • Contracts with vendors
    • Generator Policy
Home Archive by category "New Road project" (Page 2)

Category: New Road project

2022 October 26 Road Mid-Morning Update Co-owner Action Required

Dorothy Li October 26, 2022 October 26, 2022New Road project roads 1

Thursday October 27th Nagle will be coming to finish our roads!  Thank you to everyone who did pray for Divine Intervention.  The escalation worked and we should be done with our roads by the end of this week. Timeline Thursday Oct. 27th 7:30 AM pave road top coat (last layer)…

Continue reading

2022 October 26 Road Update

Dorothy Li October 26, 2022 October 26, 2022New Road project roads 0

Since last Friday the 21st, Nagle project manager and our ETC Site manager have been AWOL.  All attempts to reach them have been unsuccessful.  The Board has escalated to the next line at Nagle.  They have explained that the rain has caused issues and they are still backlogged.  The Board…

Continue reading

2022 October 20 Road Update

Dorothy Li October 20, 2022 October 20, 2022New Road project roads 0

Nagle let us know they will not be coming this week.  They plan on scheduling us for next week.  Right now, the plan is not to show up on Monday.  If they do come on Monday, they will let us know Sunday to ensure we can move our cars.  We’ll…

Continue reading

2022 October 18 Road Update

Dorothy Li October 18, 2022 October 18, 2022New Road project, Services roads 0

Nagle let us know that they are working on scheduling for the last top layer.  We requested to have this Friday or Saturday October 20th or 21st.  They have not confirmed.  We will follow up again on Thursday with an update.  Our ETC site manager let us know that next…

Continue reading

2022 October 13 Road Update

Dorothy Li October 13, 2022 October 13, 2022New Road project roads 0

Nagle let us know today that they will not be here Friday or Saturday.  They also removed the machinery from our site.  They have not received the schedule for next week so we will need to wait until Monday to find out if we are on the list to be…

Continue reading